Are you negotiating Project completion-related clauses comprehensively in SITC Contracts?
- Arvind Dang
- Apr 2
- 6 min read

This article includes the following aspects.
What are the implications in case project completion checklists are non-
Comprehensive?
2. What are nine key activities that must be carried out before initiating the project sign off
3 Five types of Checklists to be negotiated by the contracts team
i) Checklists for Risk Avoidance
ii) checklists for Critical Design & Documentation to Collect
iii) checklists for Regulatory Compliance & Approvals
iv ) checklists for Final Payment Release
v ) checklists for change management & contract adjustment
4. Common pitfalls in negotiation related to project completion clauses
5. What must be included in the Agreement to make it robust ?
1. What are the eight implications if project completion checklists are non-comprehensive?
In SITC contracts, the completion of the project isn't just about installation—it’s about ensuring the system is fully functional, tested, and commissioned as per agreed performance parameters
Therefore, project completion-related clauses must be drafted comprehensively. With each contractor
Listed below are eight adverse implications in the case of the inadequacy of clauses
✔️ 1 Unverified Installations – Equipment may be improperly installed, leading to breakdowns, costly rework, and penalties
✔️ 2 Testing & Commissioning Gaps—If systems are not tested under real operating conditions, failures may emerge after completing the project.
✔️ 3 Payment Disputes with contractors – Delays vis-à-vis project completion milestones
✔️ 4 Legal & Warranty Issues – Missing clauses & their documentation can weaken contract enforcement and void warranties.
✔️ 5 Unresolved Snag Lists – Small pending issues can escalate into major operational failures.
✔️ 6 Post-handover failures leading to financial losses.
✔️ 7 Non-compliance with contract terms
✔️ 8 Legal liabilities due to incomplete documentation and non-compliances
2 What are nine key activities that must be carried out before initiating project sign off
Obtain the project completion checklist and 13 types of as-built drawings (soft copy + 3 original hard signed copies )from the SITC contractor.
Takeover of Catalogues of the equipment under the scope of the contractor for operations & maintenance purposes
Takeover of Subcontractor’s and vendor’s purchase orders/contracts or agreements signed by the principal contractor for the client’s project for future reference
Obtain list and physical availability of tools, essential spares, documents & reports in relation to SITC-work under the scope of the contractor
Collect All Warranty certificates with validity periods
Collect Annual maintenance contracts if awarded
Obtain Statutory certifications & payments made/returns filed
Physical handover of the project to the client
Training of the Facility management for equipment operations & maintenance, etc
To accomplish the above, the Contract team must negotiate with each contractor ,5 types of checklists and incorporate these as essential clauses as per the following details.
3–Five types of Checklists to be negotiated
Five Checklists to be prepared (containing 24 aspects) for
Risk Avoidance (6 aspects)
Critical Design & Documentation collection (3 aspects with 13 types of design/drawing documents)
Regulatory Compliance & Approvals (4 aspects)
Final Payment Release (8 aspects)
Change management & contract adjustment-related aspects (3 aspects)
3(i) Contents of checklists for risk avoidance

6 aspects
Negotiate & incorporate the below clauses in the agreement with each contractor as per the scope of work in the SITC Contract
✔️1 Physical completion verification
✔️ 2 Bill of materials/quantities approval
✔️ 3 Testing & commissioning approval
✔️ 4 Final inspection & snag list clearance
✔️ 5 Warranty liability confirmation for supplies related to the contract
✔️ 6 Defect liability confirmation for activities related to installation, testing, and commissioning
3(ii) Contents of checklists for critical Design & Documentation to be collected
3 aspects

Negotiate & incorporate the below clauses in the agreement of each contractor vis-à-vis the scope of work in the SITC Contract
✔️ 1 As-built drawings & system layouts (13 types identified )
✔️ 2 Equipment manuals & O&M guidelines
✔️ 3 Spare parts & inventory lists
The suggested 13 types of designs & drawings to be collected are listed in the next slide.
13 types of designs & drawings
The suggested 13 types of designs & drawings to be collected from a Principal contractor ( for a manufacturing project) are listed below, subject to applicability as per the scope of work.
General Arrangement (GA) Drawings
Process Flow Diagrams
Piping and Instrumentation Diagrams:
Piping,
Valves,
Instruments,
Control systems for processes like cooling, lubrication, and compressed
And so on
Electrical Layout Drawings:
Power distribution diagrams,
Lighting layouts,
Control panels,
Cable routing,
Power requirements for machinery and utility systems.
And so on
Structural Drawings for laying heavy equipment, including material handling
Mechanical Equipment Layouts
HVAC and Ventilation Drawings
Utility and Service Drawings
Material Handling Drawing
Conveyors
Robots
Automated guided vehicles etc
And so on
Control System Drawings
Fabrication and Assembly Drawings for: a)Custom-built equipment/SPM
b)Jigs & fixtures c) Tooling and so on
12. Safety and Compliance Drawings
13. Detailed 3D Models (Optional & if possible)
3(iii) Contents of checklists for Regulatory Compliance & Approvals (subject to applicability

4 aspects
Negotiate & incorporate the below aspects in the agreement of each contractor vis a vis the scope of work in the SITC contract .
✔️1 Design & Plan Approvals – Ensure all drawings, layouts, and specifications are sanctioned by relevant authorities.
✔️ 2 Work-in-Progress (WIP) Approvals – Obtain necessary stage-wise inspections and compliance certificates during project execution as per local regulatory bodies
✔️3 Statutory Returns & Fees Paid – Verify payment of government levies and local authority fees.
✔️ 4 Final Regulatory Sign-Offs – Ensure occupation & completion certificates, fire safety approvals, pollution control compliance, environment clearances and other aspects are secured.
3(iv) Contents of checklists for Final Payment Release

8 aspects
Negotiate & incorporate the below aspects in the agreement with each contractor vis a vis the scope of SITC work.
✔️1 Recovery of liquidated damages for late completion
✔️ 2 Retention of a portion of the payment until the final acceptance is confirmed
✔️ 3 Availability of Performance Guarantees with appropriate extended period towards works/ package performance and warranties/defect liabilities post-installation
✔️ 4 Ensure Payment reconciliations
✔️ 5 Carry out client-supplied material reconciliations✔️ 6 Recovery of insurance claims lodged by a contractor on behalf of the client
✔️ 7 Availability of formal signing off of the measurement books for works accepted.
✔️8 Complying with all contract obligations
3(v) Contents of checklists for Change Management & Contract Adjustments
The contract team must carry out the following 3 activities related to change management, in consultation with the project team

Evolve Procedures for handling changes in scope, design, or schedule.
Determine the Approval process for change orders.
Methodology to assess the Impact assessment of changes on cost and timeline
Once the above has been done, change management-related check list/clauses need to be developed and incorporated as mentioned in the following slide
3 aspects
Negotiate & incorporate the below clauses in the agreement. of each contractor vis a vis scope of the SITC contract
✔️1 Approved variation orders-methodology
✔️ 2 Regulatory compliance approvals
✔️ 3 Updated computation for the amount payable towards changes in :
Design of the project
Scope of work,
Associated bill of materials
Installation, testing & commissioning services,
Associated equipment & manpower
Substitute materials,
vii Excess authorised consumption of the bill of materials
4. Four Common pitfalls in negotiation related to project completion clauses
✔️1 Vague wording of clauses
✔️ 2 Responsibilities of contractors not defined explicitly✔️ 3 Timelines for each milestone—supply, installation, testing, commissioning & handover of completed project not defined clearly in the agreement
✔️ 4 Exact procedures, criteria, and authority for acceptance not defined completely/clearly in the agreement
5. What must be included in the Agreement to make it robust? -90 clauses
The negotiating team must ensure a comprehensive agreement containing
Capturing of approved scope at each line item level for supply as well as SITC
Detailed bill of quantity with rates /Prices and approved brands and escalation methodology, pricing approach for substitute items /extra items
Duration of agreement, value, and validity period
Quality standards applicable to BOM equipment & work in progress, and end product, inspection & testing requirements
Project milestones, coordination with other site contractors, and a monitoring mechanism
Payment & other terms and prerequisites for RA (running account) bill passing, and methodology for QS (quantity survey) /quantity measurements and certifications.
Obligations of contractors and clients,
Define clear escalation and dispute resolution mechanisms
Tender including drawing and specification, Clarifications (both technical & commercial)
Quotes of this approved contractor with whom the agreement to be executed
All communications, including those related to Negotiation
Legal and statutory clauses and requirements, compliance updates, confidentiality, health & safety, jurisdiction, termination clauses
Responsibilities for signing agreements,
Amendments to the agreements (approving authority), and so on
As per compilation by this author, overall, a robust agreement must cover 90 clauses related to Inspection, testing & commissioning based on the above aspects.(In addition to 50 clauses related to the supply of materials, domestic + Imports covered in my earlier YT presentations)
Of course, more clauses can be added based on Industry-specific & Package specific considerations.
Want to Master Contract Negotiation? Learn with Me!
Effective contract negotiation is key to avoiding costly disputes, project delays, cost overruns and ensuring smooth project completion.